Skip to main content

Saint-Patrick Hermin, Tangry, Hestrus, Valhuon, Huclier

Operational project

Location

Hermin, Tangry, Hestrus, Valhuon, Huclier, Pas-de-Calais, France

Description

  • Commissioning dateFebruary 2010
  • Installed capacity34.5 MW
  • Around 40,000* inhabitants Supplied with electricity

  • 15 Wind turbines

  • Around 3,900* tons of CO2 Avoided annually

Techniciens et techniciennes face à une éolienne

Technical data

  • TurbinesSiemens SWT-2,3-93
  • Rotor speed6 to 16 rpm
  • Rotor diameter93 m
  • Platform height82 m

About Boralex

All you need to know about Boralex's activity worldwide.

Explore

Technicien souriant

About the Saint-Patrick Wind Farm

Located in the heart of Pas-de-Calais, the Saint-Patrick wind farm reflects Boralex’s commitment to sustainable renewable energy. Comprising 15 wind turbines, it has a total capacity of 34.5 MW.

Since its commissioning in 2010, it has met the annual energy needs of 40,000* residents. In addition to its energy performance, the site helps avoid the emission of 3,900* tonnes of CO₂, further strengthening its positive environmental impact.

Follow our News in France and Around the World

 

A question on wind energy ? 

Contact our team

Parc éolien d'Ally-Mercoeur en France exploité par Boralex

*Sources for France : ADEME, CRE, and RTE. Consumption per inhabitant: Average consumption across all uses