Operational project

Location

Tillbury, Ontario, Canada

Description

  • Commissioning dateJanuary 2009
  • Contract duration20 years
  • Installed capacity90 MW
  • 45 Wind turbines

Employée sur le toit d'une éolienne levant les bras

Technical data

  • TurbinesEnercon E82
  • Rotor diameter82 m
  • Platform height78 m
  • Blade size41 m

About Boralex

All you need to know about Boralex's activity worldwide.

This way

Technicien souriant

Thames River wind farm
at a glance

Thames River is developed in two phases. Phase 1 is composed of 4 wind sites (Bisnett Line, Front Line, Marsh Line and Swanton Line) totaling 40 MW installed capacity. It was commissioned in 2009. Phase 2 is composed of 5 wind sites (Gracey, Naylor, North Malden, Richardson and South Side) totaling 50 MW installed capacity. It was commissioned in 2010.

  • Both phases of the Thames River site are covered by a 20-year power purchase agreement with Ontario Power Authority.